Implementation Schedule and Documents
Project Implementation Schedule
An implementation strategy was adopted in October 2011 that defined phases of design and construction projects throughout the community based on flood risk priorities. West Thornhill Flood Control is a consistent with principles of Markham’s asset management plan for stormwater infrastructure, including meeting desired level of service related to flood risk mitigation.
Area | Proposed Implementation Schedule | Status |
Phase 1A: Bayview Glen Area | 2014 — 2015 | Substantially completed as of Nov 2015; Maintenance completion Nov 2017 |
Phase 1B: Bayview Glen Area | 2015 — 2016 | Substatianlly completed as of Aug 2016; Maintenance completion Aug 2018 |
Phase 1C: Canadiana Road | 2016 | Substantially completed as of Dec 2016; Maintenance completion Dec 2018 |
Phase 2A: Grandview Area | 2016 — 2017 | Substantially completed as of Dec 2016; Maintenance completion Dec 2018 |
Phase 2B: Grandview Area (Park & Proctor Ave) | 2017 — 2018 | Substantially completed as of Dec 2017; Maintenance completion Dec 2019 |
Phase 2C: Grandview Area | 2018 — 2019 | Substantially completed as of Nov 2019; Maintenance completion Nov 2021 |
Phase 2D: Grandview Area | 2019 — 2020 | Substantially completed as of Nov 2019; Maintenance completion Nov 2021 |
Phase 3A: Clark Ave./Henderson Area (This Area) | 2020 | Construction Commencement April 2020 |
Phase 3B & 3C: Clark Ave./Henderson Area | 2021— 2022 | |
Phase 4: Royal Orchard Area | 2021 & 2023 — 2026 |
Related Information:
- West Thornhill Stormwater Flood Control Implementation Strategy (West Thornhill Stormwater Flood Control Implementation Strategy)— see Report and Presentation
- Presentation to GC (October 31, 2011) — see Excerpt
- Presentation to Council (October 31, 2011) — see Presentation
- Council Resolution (November 8, 2011)— see Resolution
- Award reports:
- Phase 1 Design (April 23, 2012)— see Report
- Phase 1A Construction Services (June 16, 2014)— see Report
- Phase 1C and Phase 2 Design (November 17, 2014) see Report. Phase 1B Construction Services (February 20, 2015) see Report
- Phase 2A & 1C Construction Administration Services (February 5, 2016)— see Report
- Phase 2A Construction Services (February 5, 2016)— see Report
- Phase 1C Construction Services (April 14, 2016)— see Report
- Phase 2B, 2C, 2D Construction Administration Services (February 6, 2017)— Report
- Phase 2B Construction Services (April 18, 2017)— see Report
- Phase 3 Design Services (May 1, 2017)— see Report
- Clean Water and Wastewater Fund (CWWF) (September 18, 2017 )— Report
- Phase 2C Construction Services (May 7, 2018)— see Report
- Phase 4 Design Services (June 12, 2018)— see Report
- Phase 2D Construction Services (February 19, 2019)— see Report
- Phase 3A Construction Services (March 2, 2020)— see Report
For more information, please contact:
Robert Muir, Manager, Stormwater
Email: rmuir@markham.ca
Phone: 905.477.7000 x 2357